Ground breaking ceremony was held on August 16, 2007.
Office foundation work and plant site preparation werefinished by the end of September.
Great weather into October has masonry work ahead of schedule for both the plant and the office.
The fast pace continues into the end of October. The race is on to get under roof before the cold, wind, rain and snow hit.
Thanksgiving weekend and the skeleton of the factory addition is up and the office expansion is enclosed.
Week befor Christmas. Made it! Office interior work progressing, plant addition enclosed and the snow hit.
January, "X" on the wall indicates removal to open into existing plant. Office and locker room well underway.
Wall gone! View from the original factory looking into the expansion. Finishing touches are being completed.
The plant is basically done! All of the inspections have been completed. The office has doubled, too!